Here is the latest from Washtenaw County Road Commission on road work in our area:
Scio Church Rd will continued to be closed between Guether Rd and Steinbach Rd for culvert replacement. Work is expected to be finished 07-28-18. A detour is posted.
Dexter-Chelsea Rd between Freer Rd and Steinbach Rd will continue to have intermittent lane closure while a DTE gas line is replaced. Work is expected to be finished 10-01-18.
North Territorial Rd will have intermittent land closures between M-52 and Pinckney Rd for crack sealing. Work is expected to be finished by 07-30-18.
Baker Rd continues to be closed for the installation of the two roundabouts at Dan Hoey Rd and Shield Rd. The project is scheduled to be completed 08-31-18. A detour is posted.
Jackson Rd at Wagner Rd will have intermittent lane closures to improve pedestrian crossings. Work is expected to be finished 08-30-18.
Jackson Rd at Stabler Rd will have intermittent lane closures for the construction of a right-turn lane. The project is expected to be finished 08-30-18.
Mast Rd will have intermittent lane closures from the City to North Territorial Rd for crack sealing. Work is scheduled to be finished 07-30-18.
Webster Church, Valentine, & Merrill Roads will have intermittent lane closures between North Territorial Rd and Barker Rd for tree trimming, ditch clearing, and road repair. Work is scheduled to be finished 008-02-18.