The latest updates on road construction in our area:
New
Pleasant Lake Rd east of Schneider Rd will have intermittent lane closures for the installation of a guardrail beginning 10-10-18. The project is expected to be completed 10-19-18.
Ongoing
Dexter-Chelsea Rd between Freer Rd and Steinbach Rd will continue to have intermittent lane closure while a DTE gas line is replaced. Work is expected to be finished 10-19-18.
Jackson Rd at Wagner Rd will have intermittent lane closures to improve pedestrian crossings. Work is expected to be finished mid-October.
Sager Rd west of Fletcher Rd will have intermittent lane closures beginning 10-04-18 for guardrail replacement. Work is expected to be finished 11-05-18.
Completed
Mast Rd has rq1eopened from North Territorial Rd to Strawberry Lake Rd with the completion of the culvert replacement.
Dan Hoey Rd is fully paved and reopened.