10-19-18 Road Construction Report

The latest updates on road construction in our area:

New

I-94 eastbound and westbound will experience nighttime lane closures (9 pm – 6 am) at Wagner Rd for bridge repair beginning 10-19-18. The work is expected to be finished 10-21-18.

Mast Rd between N Territorial and Strawberry Lake Rd will have lane restrictions due to repaving beginning 10-25-18. The road will remain open but motorists should expect delays while the work is being done. The project is expected to be finished 10-30-18.

Pleasant Lake Rd east of Schneider Rd will have intermittent lane closures due to the installation of a new guardrail beginning 10-22-18. The work is expected to be finished 10-26-18.

Ongoing

Dexter-Chelsea Rd between Freer Rd and Steinbach Rd will continue to have intermittent lane closure while a DTE gas line is replaced. Project end is yet to be determined.

Jeffords Street from the alley (behind the PNC/Hackney Hardware) to the corner of Forest and Broad will be closed starting 10-11-18 and is expected to reopen 11-08-18. The street will be open Sundays during construction. The alley behind PNC Bank and Hackney Hardware will remain open.

More from Discover Communities

Local Action, Global Results – Rotary’s Effort Is Ending Polio

In a crowded plaza, in an underdeveloped country, a vaccination team is...
Read More